Question: Prepare a material requirements plan for component D. D can only be ordered in whole cases (50 units per case). One case of D is
Prepare a material requirements plan for component D. D can only be ordered in whole cases (50 units per case). One case of D is automatically received every other week, beginning in week 1 (i.e., weeks 1, 3, 5, 7). Also, there are 30 units of B and 20 units of D now on hand. Lead times for all items are a function of quantity: one week for up to 100 units, two weeks for 101 to 200 units, three weeks for 201 to 300 units, and four weeks for 301 or more units.
| Part D | Beg. Inv. | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
| Gross requirements | |||||||||
| Scheduled receipts | |||||||||
| On hand | |||||||||
| Net requirements | |||||||||
| Planned-order receipt | |||||||||
| Planned-order release | |||||||||