Question: Prepare a material requirements plan for component Q using the information below, and tell me how many units you need to order in the first
Prepare a material requirements plan for component Q using the information below, and tell me how many units you need to order in the first 5 weeks: Item X uses quantity two (2) of component Q Eighty units of end item X are needed at the beginning of week 6, and another 30 units are needed at the beginning of week 8. Q can only be ordered in whole cases (20 units per case). You have no recurring orders set up for Component Q Week 1, you started without any units of Q in stock Lead time for Q is 2 weeks Question 8 options: 30 60 80 160