Question: prepare a Precedence Diagram, calculate the duration for each path, identify the critical path, calculate and identify the ES, EF, LS, and LF for each
-
prepare a Precedence Diagram,
-
calculate the duration for each path,
-
identify the critical path,
-
calculate and identify the ES, EF, LS, and LF for each task, and
-
calculate and identify the slack time for each task, for the following project:
Project tasks
-
There are ten total tasks, named AJ.
-
Tasks A, B, and H have durations of two days.
-
Tasks C, E, I, and J have durations of three days.
-
Tasks D, F, and G have durations of one day.
-
Tasks A, C, D and F have no dependencies.
-
Task B cannot start until task C has finished.
-
Tasks A and F must finish before Task E can start.
-
Task E must finish before Task G starts.
-
Task H cannot start until Task B has finished, and Task D must finish before Task I starts.
-
Tasks G, H, and I must finish before Task J can start.