Question: Prepare a schedule based on resources. There are only 3 resources available for each period. Please explain this step by step Activity Predecessor Duration Resources

Prepare a schedule based on resources. There are only 3 resources available for each period.

Please explain this step by step

Activity Predecessor Duration Resources needed
1 - 2 2
2 1 6 2
3 1 4 2
4 1 2 1
5 3 2 1
6 3 4 1
7 2,4,5,6 2 1

1. What is the critical path before resource assignment?

2. What will be the project duration after resources are assigned?

3. What will be the final slack for activity 2?

4. What will be the final slack for activity 6?

5. Which activity starts first between 2, 3, and 4? Why?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!