Question: Present a grant chart and step by step approach to create the same in excel for the below data. It needs to be presentable Please


Present a grant chart and step by step approach to create the same in excel for the below data.
It needs to be presentable
Please find the below project schedule.
| Task | Precedences | Start Date | Days to complete |
| 1.ProjectInitiation: | |||
| 1.1ProjectKick-offMeeting | None | 15/08/2023 | 1 |
| 1.1.1ProjectKick-offMeetingAgenda | None | 15/08/2023 | 1 |
| 1.2DefineProjectObjectivesandScope | Project Kick-off Meeting | 17/08/2023 | 2 |
| 1.2.1ProjectObjectivesDocument | Project Kick-off Meeting | 17/08/2023 | 2 |
| 1.3IdentifyKeyStakeholders | DefineProjectObjectivesandScope | 20/08/2023 | 3 |
| 1.4DevelopProjectCharter | IdentifyKeyStakeholders | 22/08/2023 | 2 |
| 1.5ObtainProjectSponsorApproval | DevelopProjectCharter | 25/08/2023 | 1 |
| 1.5.1ProjectSponsorApprovalDocument | DevelopProjectCharter | 25/08/2023 | 1 |
| 1.6DevelopCommunicationPlan | ObtainProjectSponsorApproval | 27/08/2023 | 3 |
| 1.7DevelopRiskRegister | DevelopCommunicationPlan | 30/08/2023 | 4 |
| 1.8DefineProjectTeamRolesandResponsibilities | DevelopRiskRegister | 01/09/2023 | 2 |
| 1.9DevelopTeamContract | DefineProjectTeamRolesandResponsibilities | 05/09/2023 | 3 |
| 1.10DevelopWorkBreakdownStructure(WBS) | DevelopTeamContract | 08/09/2023 | 5 |
| 1.10.1WorkBreakdownStructure(WBS)Draft | DevelopTeamContract | 08/09/2023 | 5 |
| 1.11CreateProjectScheduleandMilestones | Develop Work Breakdown Structure (WBS) | 12/09/2023 | 4 |
| 1.11.1ProjectScheduleandMilestonesReport | Develop Work Breakdown Structure (WBS) | 12/09/2023 | 4 |
| 1.12DevelopProjectBudgetandCostBaseline | CreateProjectScheduleandMilestones | 15/09/2023 | 3 |
| 1.13ObtainStakeholderApprovals | DevelopProjectBudgetandCostBaseline | 18/09/2023 | 2 |
| 1.13.1StakeholderApprovalDocumentation | DevelopProjectBudgetandCostBaseline | 18/09/2023 | 2 |
| 2.PlanningPhase: | Obtain Stakeholder Approvals | 20/09/2023 | 3 |
| 2.1ConductStakeholderAnalysis | Obtain Stakeholder Approvals | 20/09/2023 | 3 |
| 2.2GatherRequirementsfromUsersandStakeholders | ConductStakeholderAnalysis | 23/09/2023 | 5 |
| 2.2.1UserandStakeholderRequirementsDocument | ConductStakeholderAnalysis | 23/09/2023 | 5 |
| 2.3CreateBusinessCase | GatherRequirementsfromUsersandStakeholders | 28/09/2023 | 4 |
| 2.3.1BusinessCaseDocument | Gather Requirements from Users and Stakeholders | 28/09/2023 | 4 |
| 2.4DevelopRiskManagementPlan | Create Business Case | 02/10/2023 | 3 |
| 2.5DefineProjectTeamRolesandResponsibilities | Develop Risk Management Plan | 05/10/2023 | 2 |
| 2.6DevelopCommunicationPlan | Define Project Team Roles and Responsibilities | 08/10/2023 | 3 |
| 2.7DevelopRiskRegister | Develop Communication Plan | 12/10/2023 | 4 |
| 2.8DevelopWorkBreakdownStructure(WBS) | Develop Risk Register | 17/10/2023 | 5 |
| 2.8.1WorkBreakdownStructure(WBS)Final | Develop Risk Register | ||
| 2.9CreateProjectScheduleandMilestones | Develop Work Breakdown Structure (WBS) | 22/10/2023 | 4 |
| 2.9.1ProjectScheduleandMilestonesReport | Develop Work Breakdown Structure (WBS) | 22/10/2023 | 4 |
| 2.10DevelopProjectBudgetandCostBaseline | Create Project Schedule and Milestones | 27/10/2023 | 3 |
| 2.11ObtainStakeholderApprovals | Develop Project Budget and Cost Baseline | 31/10/2023 | 2 |
| 2.11.1StakeholderApprovalDocumentation | Develop Project Budget and Cost Baseline | 31/10/2023 | 2 |
| 3.AnalysisandDesignPhase: | Obtain Stakeholder Approvals | 05/11/2023 | 7 |
| 3.1ConductUserInterviewsandSurveys | Obtain Stakeholder Approvals | 05/11/2023 | 7 |
| 3.1.1UserInterviewandSurveyReports | Obtain Stakeholder Approvals | 05/11/2023 | 7 |
| 3.2AnalyzeCurrentHRDataManagementProcesses | Conduct User Interviews and Surveys | 13/11/2023 | 5 |
| 3.3DefineHRISSystemRequirements | Analyze Current HR Data Management Processes | 20/11/2023 | 6 |
| 3.3.1HRISSystemRequirementsDocument | Analyze Current HR Data Management Processes | 20/11/2023 | 6 |
| 3.3.1.1Detailedfunctionalrequirements | Analyze Current HR Data Management Processes | ||
| 3.4DevelopSystemDesignDocument | Define HRIS System Requirements | 27/11/2023 | 8 |
| 3.4.1SystemDesignDocument | Define HRIS System Requirements | 27/11/2023 | 8 |
| 3.4.1.1Technicalspecificationsdocument | SystemDesignDocument | ||
| 3.5CreateWireframesandPrototypesforUserInterface | Develop System Design Document | 05/12/2023 | 7 |
| 3.6ReviewandApproveDesignwithStakeholders | Create Wireframes and Prototypes for User Interface | 13/12/2023 | 3 |
| 3.7DevelopProductDesignandArchitecture | Review and Approve Design with Stakeholders | 18/12/2023 | 9 |
| 3.7.1ProductDesignandArchitectureDocument | Review and Approve Design with Stakeholders | 18/12/2023 | 9 |
| 4.DevelopmentPhase: | Obtain Stakeholder Approvals | 28/12/2023 | 3 |
| 4.1SetUpDevelopmentEnvironmentandTools | Obtain Stakeholder Approvals | 28/12/2023 | 3 |
| 4.2CreateDatabaseStructureforHRIS | Set Up Development Environment and Tools | 02/01/2024 | 5 |
| 4.3DevelopFront-EndUserInterface | Create Database Structure for HRIS | 09/01/2024 | 10 |
| 4.4ImplementBack-EndDataProcessingLogic | Develop Front-End User Interface | 19/01/2024 | 12 |
| 4.5IntegrateUserInterfaceandDataProcessingModules | Implement Back-End Data Processing Logic | 01/02/2023 | 8 |
| 4.6ConductUnitTestingofApplicationComponents | Integrate User Interface and Data Processing Modules | 09/02/2024 | 10 |
| 4.6.1UnitTestingReport | Integrate User Interface and Data Processing Modules | 09/02/2024 | 10 |
| 4.6.1.1Testcasesandresults | |||
| 4.7ResolveBugsandIssuesIdentifiedinTesting | Conduct Unit Testing of Application Components | 20/02/2024 | 6 |
| 4.7.1BugandIssueResolutionDocument | Conduct Unit Testing of Application Components | 20/02/2024 | 6 |
| 4.8ConductCodeReviewandDocumentation | Resolve Bugs and Issues Identified in Testing | 27/02/2024 | 5 |
| 4.9ObtainStakeholderReviewandApproval | Conduct Code Review and Documentation | 03/03/2024 | 3 |
| 4.10CreateResearchReports | Obtain Stakeholder Review and Approval | 07/03/2024 | 4 |
| 4.11DevelopDesignDocuments | Create Research Reports | 12/03/2024 | 5 |
| 4.12WriteSoftwareCode | Develop Design Documents | 18/03/2024 | 15 |
| 4.13AssembleHardwareComponents | Write Software Code | 02/04/2024 | 8 |
| 5.TestingPhase: | Assemble Hardware Components | 10/04/2024 | 5 |
| 5.1PrepareTestCasesandTestData | Assemble Hardware Components | 10/04/2024 | 5 |
| 5.2ConductSystemIntegrationTesting | Prepare Test Cases and Test Data | 16/04/2024 | 12 |
| 5.2.1SystemIntegrationTestingReport | Prepare Test Cases and Test Data | 16/04/2024 | 12 |
| 5.2.1.1Testscenariosandresults | |||
| 5.3PerformPerformanceTesting | Conduct System Integration Testing | 28/04/2024 | 7 |
| 5.4ConductFunctionalTesting | Perform Performance Testing | 06/05/2024 | 8 |
| 5.5PerformUsabilityTesting | Conduct Functional Testing | 15/05/2024 | 6 |
| 5.6ConductUserAcceptanceTesting(UAT) | Perform Usability Testing | 22/05/2024 | 12 |
| 5.6.1UserAcceptanceTesting(UAT)Report | Perform Usability Testing | 22/05/2024 | 12 |
| 5.6.1.1Level3:UATtestcasesandresults | |||
| 5.7AddressandResolveDefectsandIssues | Conduct User Acceptance Testing (UAT) | 03/06/2024 | 8 |
| 5.7.1DefectsandIssuesLog | Conduct User Acceptance Testing (UAT) | 03/06/2024 | 8 |
| 5.8ObtainUATSign-OfffromStakeholders | Address and Resolve Defects and Issues | 12/06/2024 | 3 |
| 6.DeploymentPhase: | Obtain UAT Sign-Off from Stakeholders | 16/06/2024 | 5 |
| 6.1PrepareDeploymentPlan | Obtain UAT Sign-Off from Stakeholders | 16/06/2024 | 5 |
| 6.2MigrateDatafromLegacySystemtoHRIS | Prepare Deployment Plan | 22/06/2024 | 10 |
| 6.3SetUpHRISServersandInfrastructure | Migrate Data from Legacy System to HRIS | 03/07/2024 | 6 |
| 6.3.1HRISServersandInfrastructureSetupDocument | Migrate Data from Legacy System to HRIS | 03/07/2024 | 6 |
| 6.4InstallandConfigureHRISApplication | Set Up HRIS Servers and Infrastructure | 10/07/2024 | 7 |
| 6.5ConductUserTrainingSessions | Install and Configure HRIS Application | 18/07/2024 | 10 |
| 6.5.1UserTrainingSessionScheduleandMaterials | Install and Configure HRIS Application | 18/07/2024 | 10 |
| 6.6MonitorandAddressDeploymentIssues | Conduct User Training Sessions | 29/07/2024 | 14 |
| 6.6.1Post-DeploymentIssueLog | Conduct User Training Sessions | 29/07/2024 | 14 |
| 6.6.2EstablishSystemMaintenanceProcedures | Monitor and Address Deployment Issues | 12/08/2024 | 8 |
| 6.6.3ProvideOngoingUserSupportandTraining | Establish System Maintenance Procedures | 22/08/2024 | Ongoing |
| 6.6.4AddressBugFixesandSystemEnhancements | Provide Ongoing User Support and Training | 01/09/2024 | Ongoing |
| 6.6.5MonitorSystemPerformanceandSecurity | Address Bug Fixes and System Enhancements | Ongoing | Continuous |
| 6.6.6ConductRegularDataBackupsandUpdates | Monitor System Performance and Security | Ongoing | Continuous |
| 7.ProjectClosurePhase: | Conduct Regular Data Backups and Updates | 15/09/2024 | 5 |
| 7.1ConductProjectReviewandLessonsLearned | Conduct Regular Data Backups and Updates | 15/09/2024 | 5 |
| 7.1.1ProjectReviewandLessonsLearnedReport | Conduct Regular Data Backups and Updates | 15/09/2024 | 5 |
| 7.2PrepareFinalProjectReport | Conduct Project Review and Lessons Learned | 21/09/2024 | 7 |
| 7.3ArchiveProjectDocumentsandArtifacts | Prepare Final Project Report | 28/09/2024 | 5 |
| 7.4ObtainProjectSponsorandStakeholderApproval | Archive Project Documents and Artifacts | 03/10/2024 | 3 |
| 7.4.1SponsorandStakeholderApprovalDocumentation | Archive Project Documents and Artifacts | 03/10/2024 | 3 |
| 7.5CelebrateProjectSuccessandAcknowledgeTeamEfforts | Obtain Project Sponsor and Stakeholder Approval | 07/10/2024 | 1 |






Task Precedences Start Date Day's t 1.ProjectInitiation: 1.1ProjectKick-offMeeting None 15/08/2023 1. 1. 1ProjectKick-offMeetingAgenda None 15/08/2023 1.2DefineProjectObjectivesandScope Project Kick-off Meeting 17/08/2023 2 1.2. 1ProjectObjectivesDocument Project Kick-off Meeting 17/08/2023 2 1.3IdentifyKeyStakeholders DefineProjectObjectivesandScope 20/08/2023 3 1.4DevelopProjectCharter IdentifyKeyStakeholders 22/08/2023 1.5ObtainProjectSponsorApproval DevelopProjectCharter 25/08/2023 1.5.1ProjectSponsorApprovalDocument DevelopProjectCharter 25/08/2023 1.6DevelopCommunicationPlan ObtainProjectSponsorApproval 27/08/2023 3 1.7DevelopRiskRegister DevelopCommunicationPlan 30/08/2023 4 1.8DefineProjectTeamRolesandResponsibilitieselopRiskRegister 01/09/2023 2 1.9Develop TeamContract DefineProjectTeamRolesandResponsibiliti 3 1.10DevelopWorkBreakdownStructure(WBS) DevelopTeamContract 08/09/2023 5 1. 10. 1WorkBreakdownStructure(WBS)Draft Develop TeamContract 08/09/2023 5 1.11CreateProjectScheduleandMilestones Develop Work Breakdown Structure (WB 12/09/2023 4 1.11. 1ProjectScheduleandMilestonesReport Develop Work Breakdown Structure (WB 12/09/2023 4 1 19navalonDriestRunstandActRacalina CrestaDriestCAhaulaandMilactAnec 15o/2072 21.11.1ProjectScheduleandMilestonesReport Develop Work Breakdown Structure (WB 12/09/2023 4 1.12DevelopProjectBudgetandCostBaseline CreateProjectScheduleandMilestones 15/09/2023 1. 13ObtainStakeholderApprovals DevelopProjectBudgetandCostBaseline 18/09/2023 1. 13. 1StakeholderApprovalDocumentation DevelopProjectBudgetandCostBaseline 18/09/2023 2. PlanningPhase: Obtain Stakeholder Approvals 20/09/2023 UI UI W W N N 2.1 ConductStakeholderAnalysis Obtain Stakeholder Approvals 20/09/2023 2.2GatherRequirementsfromUsersandStakeh ConductStakeholderAnalysis 23/09/2023 2.2. 1UserandStakeholderRequirementsDocur ConductStakeholderAnalysis 23/09/2023 2.3CreateBusinessCase GatherRequirementsfromUsersandStaker 28/09/2023 2.3. 1 BusinessCaseDocument Gather Requirements from Users and Sta 28/09/2023 4 2.4DevelopRiskManagementPlan Create Business Case 02/10/2023 2.5DefineProjectTeamRolesandResponsibilitieselop Risk Management Plan 05/10/2023 2 2.6DevelopCommunicationPlan Define Project Team Roles and Responsi 08/10/2023 3 2.7DevelopRiskRegister Develop Communication Plan 12/10/2023 4 2.8DevelopWorkBreakdownStructure(WBS) Develop Risk Register 17/10/2023 5 2.8.1WorkBreakdownStructure(WBS)Final Develop Risk Register 2.9CreateProjectScheduleandMilestones Develop Work Breakdown Structure (WB 22/10/2023 4 2.9.1ProjectScheduleandMilestonesReport Develop Work Breakdown Structure (WB 22/10/2023 4 2.10DevelopProjectBudgetandCostBaseline Create Project Schedule and Milestones 27/10/2023 NW 2.11ObtainStakeholderApprovals Develop Project Budget and Cost Baselin 31/10/2023 2. 11. 1 StakeholderApprovalDocumentation Develop Project Budget and Cost Baselin 31/10/2023 3.AnalysisandDesignPhase: Obtain Stakeholder Approvals 05/11/2023 3 1Conductl learInterviewsandSurvieve Ohtain Stakeholder Annrovale 05/11/2023 72. 11. 1StakeholderApprovalDocumentation Develop Project Budget and Cost Baselin 31/10/2023 3.AnalysisandDesignPhase: Obtain Stakeholder Approvals 05/1 1/2023 3. 1 ConductUserInterviewsandSurveys Obtain Stakeholder Approvals 05/1 1/2023 3.1. 1UserInterviewandSurveyReports Obtain Stakeholder Approvals 05/11/2023 3.2AnalyzeCurrentHRDataManagementProce Conduct User Interviews and Surveys 13/11/2023 5 3.3DefineHRISSystemRequirements Analyze Current HR Data Management Pi 20/11/2023 3.3. 1HRISSystemRequirementsDocument Analyze Current HR Data Management Pi 20/11/2023 6 3.3. 1. 1Detailedfunctionalrequirements Analyze Current HR Data Management Processes 3.4DevelopSystemDesignDocument Define HRIS System Requirements 27/11/2023 8 3.4.1SystemDesignDocument Define HRIS System Requirements 27/11/2023 3.4. 1. 1Technicalspecificationsdocument SystemDesignDocument 3.5CreateWireframesandPrototypesforUserlr Develop System Design Document 05/12/2023 w 3.6ReviewandApproveDesignwithStakeholder Create Wireframes and Prototypes for Us 13/12/2023 3.7DevelopProductDesignandArchitecture Review and Approve Design with Stakehc 18/12/2023 9 3.7.1ProductDesignandArchitectureDocument Review and Approve Design with Stakehc 18/12/2023 4.DevelopmentPhase: Obtain Stakeholder Approvals 28/12/2023 4.1SetUpDevelopmentEnvironmentandTools Obtain Stakeholder Approvals 28/12/2023 4.2CreateDatabaseStructureforHRIS Set Up Development Environment and To: 02/01/2024 5 4.3DevelopFront-EndUserInterface Create Database Structure for HRIS 09/01/2024 10 4.4ImplementBack-EndDataProcessingLogic Develop Front-End User Interface 19/01/2024 12 4.5IntegrateUserInterfaceandDataProcessing Implement Back-End Data Processing Lo 01/02/2023 8 4.6ConductUnitTestingofApplicationCompone Integrate User Interface and Data Proces 09/02/2024 10 4.6. 1UnitTestingReport Integrate User Interface and Data Proces 09/02/2024 104.6. 1UnitTestingReport Integrate User Interface and Data Proces 09/02/2024 10 4.6.1. 1Testcasesandresults 4.7ResolveBugsandIssuesIdentifiedinTesting Conduct Unit Testing of Application Comp 20/02/2024 6 4.7. 1 BugandIssueResolutionDocument Conduct Unit Testing of Application Comp 20/02/2024 6 4.8ConductCodeReviewandDocumentation Resolve Bugs and Issues Identified in Tes 27/02/2024 5 4.9ObtainStakeholderReviewandApproval Conduct Code Review and Documentation 03/03/2024 3 4. 10CreateResearchReports Obtain Stakeholder Review and Approval 07/03/2024 4 4. 1 1 DevelopDesignDocuments Create Research Reports 12/03/2024 5 4.12WriteSoftwareCode Develop Design Documents 18/03/2024 15 4. 13AssembleHardwareComponents Write Software Code 02/04/2024 8 5. TestingPhase: Assemble Hardware Components 10/04/2024 5 5.1Prepare TestCasesandTestData Assemble Hardware Components 10/04/2024 5 5.2ConductSystemintegration Testing Prepare Test Cases and Test Data 16/04/2024 12 5.2.1Systemintegration TestingReport Prepare Test Cases and Test Data 16/04/2024 12 5.2. 1. 1Testscenariosandresults 5.3PerformPerformanceTesting Conduct System Integration Testing 28/04/2024 7 5.4ConductFunctionalTesting Perform Performance Testing 06/05/2024 8 5.5PerformUsability Testing Conduct Functional Testing 15/05/2024 6 5.6ConductUserAcceptanceTesting(UAT) Perform Usability Testing 22/05/2024 12 5.6. 1UserAcceptanceTesting(UAT)Report Perform Usability Testing 22/05/2024 12 5.6. 1. 1Level3:UATtestcasesandresults 5.7 AddressandResolveDefectsandIssues Conduct User Acceptance Testing (UAT) 03/06/2024 18 5.7.1DefectsandIssuesLog Conduct User Acceptance Testing (UAT) 03/06/2024 85.7 AddressandResolveDefectsandIssues Conduct User Acceptance Testing (UAT) 03/06/2024 8 5.7.1DefectsandIssuesLog Conduct User Acceptance Testing (UAT) 03/06/2024 8 5.8ObtainUATSign-OfffromStakeholders Address and Resolve Defects and Issues 12/06/2024 3 6.DeploymentPhase: Obtain UAT Sign-Off from Stakeholders 16/06/2024 5 6. 1 PrepareDeploymentPlan Obtain UAT Sign-Off from Stakeholders 16/06/2024 5 6.2MigrateDatafromLegacySystemtoHRIS Prepare Deployment Plan 22/06/2024 10 6.3SetUpHRISServersandInfrastructure Migrate Data from Legacy System to HR| 03/07/2024 6 6.3.1HRISServersandInfrastructureSetupDoc Migrate Data from Legacy System to HR| 03/07/2024 6 6.4InstallandConfigureHRISApplication Set Up HRIS Servers and Infrastructure 10/07/2024 7 6.5ConductUserTrainingSessions Install and Configure HRIS Application 18/07/2024 10 6.5. 1UserTrainingSessionScheduleandMateri: Install and Configure HRIS Application 18/07/2024 10 6.6MonitorandAddressDeploymentIssues Conduct User Training Sessions 29/07/2024 14 6.6.1Post-DeploymentIssueLog Conduct User Training Sessions 29/07/2024 14 6.6.2EstablishSystemMaintenanceProcedure: Monitor and Address Deployment Issues 12/08/2024 8 6.6.3ProvideOngoingUserSupportandTraining Establish System Maintenance Procedure 22/08/2024 ngoing 6.6.4AddressBugFixesandSystemEnhanceme Provide Ongoing User Support and Trainil 01/09/2024 ngoing 6.6.5MonitorSystemPerformanceandSecurity Address Bug Fixes and System Enhancer Ongoing tinuous 6.6.6ConductRegularDataBackupsandUpdate Monitor System Performance and Securit Ongoing tinuous 7.ProjectClosurePhase: Conduct Regular Data Backups and Upda 15/09/2024 5 7.1ConductProjectReviewandLessonsLearned Conduct Regular Data Backups and Upda 15/09/2024 5 7.1.1ProjectReviewandLessonsLearnedRepo Conduct Regular Data Backups and Upda 15/09/2024 5 7.2PrepareFinalProjectReport Conduct Project Review and Lessons Lea 21/09/2024 7 7.3ArchiveProjectDocumentsandArtifacts Prepare Final Project Report 28/09/2024 54 7.4ObtainProjectSponsorandStakeholderAppi Archive Project Documents and Artifacts 03/10/2024 3 5 7.4. 1 SponsorandStakeholderApprovalDocum Archive Project Documents and Artifacts 03/10/2024 1 7.5CelebrateProjectSuccessandAcknowledge Obtain Project Sponsor and Stakeholder / 07/10/2024 6
Step by Step Solution