Question: Present clean and clear solutions to the following problems. Do not forget to highlight the final answer. Wastewater from an industrial plant was tested in

Present clean and clear solutions to the following problems. Do not forget to highlight the final answer.
Wastewater from an industrial plant was tested in a pilot activated sludge plant, and the kinetic constants were calculated as:
Maximum growth rate constant =5 day1,
Yield =0.4,
Half saturation constant =200 mg/L
The influent BOD is 1500 mg/L, and a flow rate of 20,000 m3/day is expected. The aerators to be used will limit the suspended solids in the aeration tank to 4000 mg/L. The available aeration volume is 5000 m3. What efficiency of BOD removal can be expected?
Properties of water at 10\deg C:
Density: 999.84 kg/m3
Viscosity: 1.310 x 10-3 kg/m-s

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!