Question: Present DurationAcceleratedDurationImmediateActivity ( Weeks ) A 1 0 B 1 5 c 1 0 D 2 0 E 1 5 F 1 7 G 1
Present DurationAcceleratedDurationImmediateActivityWeeksABcDEFGWeeksPredecessorActivitiesPresentCost$AACBBD FG HAcceleratedCost$Develop a timecost tradeoff analysis. Detail the steps that you would use to accelerate or crash the project to its minimum duration at the lowest cost. Determine each step's cost and the duration of the project.