Question: Consider a project having the following seven activities: Immediate Activity Predecessors Time (weeks) A none 3 B A 5 C B 4 D B 5

Consider a project having the following seven activities: Immediate Activity Predecessors Time (weeks) A none 3 B A 5 C B 4 D B 5 E C 3 F D 8 G E, F 3 (a) What is the critical time? Consider a project having the following seven activities: Immediate Activity Predecessors Time

1. Consider a project having the following seven activities: Activity A B C D E F G Immediate Predecessors none A B B C D E, F Time (weeks) 3 5 4 5 3 8 3 1. Consider a project having the following seven activities: Activity A B C D E F G Immediate Predecessors none A B B C D E, F Time (weeks) 3 5 4 5 3 8 3