Question: Presented below are data relating to labor for Verde Appliance Repair Shop Repair-technicians' wages $142,051 Fringe benefits 35,046 Overhead 71,004 10 The desired profit margin

 Presented below are data relating to labor for Verde Appliance Repair

Presented below are data relating to labor for Verde Appliance Repair Shop Repair-technicians' wages $142,051 Fringe benefits 35,046 Overhead 71,004 10 The desired profit margin per hour $18.95 The materiading charges 10% of invece cost. Verde estimates that 5.100 labor hours will be worved nest year I Verder takes 14 hours to repair and use parts of $74.06, compute the bill for the job. (Round answer to 2 decimales, 10.50) Total cost