Question: Previous Page Next Page Question 5 (2 points) A direct labour efficiency variance cannot be caused by: A) Poor quality raw materials B) Producing fewer
Previous Page Next Page Question 5 (2 points) A direct labour efficiency variance cannot be caused by: A) Poor quality raw materials B) Producing fewer finished units than originally planned C) Employee inefficiency D) An out-of-date labour time standard