Question: Prior to a mllestone review, the GOLIATH program discovers that a Nunn McCurdy cost breach is epected to oosur with respest to its Program Asquisition
Prior to a mllestone review, the GOLIATH program discovers that a Nunn McCurdy cost breach is epected to oosur with respest to its Program Asquisition Unit Cost (PAUG). Over the neXt thirty days, the GOLIATIH Pregram Manager will meat IIkaly ba required to de which of the follOwing? (Select three.] A. Notity the MDA B. Notity the componerit leadership C. Subni! a ProgRAM Deviation Report (PDR) D. InForm the HASC and SASC