Question: Prior to beginning work on this learning activity, review the following webpages CPM - Critical Path Method Links to an external site., Gantt Chart Links
Prior to beginning work on this learning activity, review the following webpages CPM - Critical Path Method Links to an external site., Gantt Chart Links to an external site., and PERT Links to an external site., and read Chapter 6: Developing a Project Schedule from your course textbook. Based on the table below, draw a project network from the following information: What activity(s) is a burst activity? What activity(s) is a merge activity? What is the critical path? Work Packages ID Description Predecessor Durations A Survey Site None 2 Days B Excavate Site A 4 Days C Install Power Lines B 3 Days D Install Drainage B 2 Days E Pour Foundation C, D 3 Days Your document should be submitted using the Waypoint link below