Question: Critical Path Prior to beginning work on this learning activity, review the following webpages CPM - Critical Path Method Links to an external site. ,
Critical Path
Prior to beginning work on this learning activity, review the following webpages CPM - Critical Path MethodLinks to an external site., Gantt ChartLinks to an external site., and PERTLinks to an external site., and read Chapter 6: Developing a Project Schedule from your course textbook.
Based on the table below, draw a project network from the following information: What activity(s) is a burst activity? What activity(s) is a merge activity? What is the critical path?
Work Packages
| ID | Description | Predecessor | Durations |
| A | Survey Site | None | 2 Days |
| B | Excavate Site | A | 4 Days |
| C | Install Power Lines | B | 3 Days |
| D | Install Drainage | B | 2 Days |
| E | Pour Foundation | C, D | 3 Days |
Here is what I have does it look correct?

6 0 A 2 0 Site Survey 0 2 2 Exavate Site 4 6 11 E 14 0 Pour Foundation 11 3 14 C 9 Install Power Lines 3 11 D 8 Install Drainage 2 8