Question: Critical Path Prior to beginning work on this learning activity, review the following webpages CPM - Critical Path Method Links to an external site. ,

Critical Path

Prior to beginning work on this learning activity, review the following webpages CPM - Critical Path MethodLinks to an external site., Gantt ChartLinks to an external site., and PERTLinks to an external site., and read Chapter 6: Developing a Project Schedule from your course textbook.

Based on the table below, draw a project network from the following information: What activity(s) is a burst activity? What activity(s) is a merge activity? What is the critical path?

Work Packages

IDDescriptionPredecessorDurations
ASurvey SiteNone2 Days
BExcavate SiteA4 Days
CInstall Power LinesB3 Days
DInstall DrainageB2 Days
EPour FoundationC, D3 Days

Here is what I have does it look correct?

Critical PathPrior to beginning work on this learning activity, review the following

6 0 A 2 0 Site Survey 0 2 2 Exavate Site 4 6 11 E 14 0 Pour Foundation 11 3 14 C 9 Install Power Lines 3 11 D 8 Install Drainage 2 8

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!