Question: Prior to preparing a monthly project status report, a project manager identifies three new risks. All of these risks could impact critical key milestones. The
Prior to preparing a monthly project status report, a project manager identifies three new risks. All of these risks could impact critical key milestones. The project manager wants to reference additional information before presenting this new risk information. To which sources should the project manager refer? SELECT THE CORRECT ANSWER Risk register and risk report Risk register and organizational process assets Risk management plan and risk report Lessons learned repository and risk report