Question: Priscilla is working for a multinational company as a project manager for the project to renovate their headquarters. The replacement of the eight main elevators
Priscilla is working for a multinational company as a project manager for the project to renovate their headquarters. The replacement of the eight main elevators has started and is progressing as planned and to budget. Half way through the project, the project manager determines that a change is needed to purchase an extended fire alarm system for the project. The project manager simply tells her team members to purchase the system immediately. This is an example of:(For Ref Only, Question #: PM-02738) Group of answer choices Lack of change control system Team building process Lack of risk assessment Decision by plurality