Question: PRO Engineering is considering whether to purchase or lease a piece of earthmoving equipment. The data associated with the purchase are as follows Initial cost
PRO Engineering is considering whether to purchase or lease a piece of earthmoving equipment.
The data associated with the purchase are as follows
Initial cost = $150,000
Residual value = $12,000
Maintenance cost = $1,800/per year
Operator cost per day = $300/day
If the equipment is rented, the operator cost is incurred, at the rate of $300 per day and $100 for the daily rental of the equipment.
Determine the minimum number of days per year the equipment must be used to justify the purchase. Use an interest rate of 7%. (10 points)
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock