Question: Problem 04-3A Applying activity-based costing LO P1, P3, A1, A2, C3 [The following information applies to the questions displayed below.] Craft Pro Machining produces machine

Problem 04-3A Applying activity-based costing LO P1, P3, A1, A2, C3

[The following information applies to the questions displayed below.] Craft Pro Machining produces machine tools for the construction industry. The following details about overhead costs were taken from its company records.

Production Activity Indirect Labor Indirect Materials Other Overhead
Grinding $ 370,000
Polishing $ 110,000
Product modification 600,000
Providing power $ 265,000
System calibration 410,000

Additional information on the drivers for its production activities follows.

Grinding 11,000 machine hours
Polishing 11,000 machine hours
Product modification 2,100 engineering hours
Providing power 21,000 direct labor hours
System calibration 1,000 batches

Job 3175 Job 4286
Number of units 140 units 1,750 units
Machine hours 250 MH 2,500 MH
Engineering hours 26 eng. hours 36 eng. hours
Batches 25 batches 75 batches
Direct labor hours 450 DLH 4,050 DLH

Problem 04-3A Part 5

Required: 5. If the company uses a plantwide overhead rate based on direct labor hours, what is the overhead cost for each unit of Job 3175? Of Job 4286? (Do not round intermediate calculations. Round "OH Cost per unit" answers to 2 decimal places.)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!