Question: Problem 1 0 - 9 ( A l g o ) Comprehensive Variance Analysis [ L O 1 0 - 1 , L O 1

Problem 10-9(Algo) Comprehensive Variance Analysis [LO10-1,LO10-2,LO10-3]
Marvel Parts, Incorporated, manufactures auto accessories including a set of seat covers that can be adjusted to fit most cars.
According to its standards, the factory should work 980 hours each month to produce 1,960 sets of-seat covers. The standard costs associated with this level of production are:
Direct materials
Direct labor
Variable manufacturing overhead (basedon
direct labor-hours)
Total
$ 32,340
$ 6,860
Per Set of
Covers
$ 16.50
3.50
$ 1,960
1.00
$ 21.00
During August, the factory worked 1,000 direct labor-hours and produced 2,100 sets of covers. The following actual costs were recorded during the month:
Direct materials (6,000 yards)
Direct labor
Variable manufacturing overhead
Total
$ 34,020
$ 7,770
$ 3,990
Per Set of Covers
$ 16.20
3.70
1.90
$ 21.80
At standard, each set of covers should require 2.5 yards of material. All of the materials purchased during the month were used in production.
Required:
Compute the materials price and quantity variances for August.
Compute the labor rate and efficiency variances for August.
Compute the variable overhead rate and efficiency variances for August.
Note: Do not round intermediate calculations. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Input all amounts as positive values.
Problem 10-9(Algo) Comprehensive Variance Analysis [LO10-1,LO10-2,LO10-3]
Marvel Parts, Incorporated, manufactures auto accessories including a set of seat covers that can be adjusted to fit most cars.
According to its standards, the factory should work 980 hours each month to produce 1,960 sets of feat covers. The standard costs
associated with this level of production are:
During August, the factory worked 1,000 direct labor-hours and produced 2,100 sets of covers. The following actual costs were
recorded during the month:
At standard, each set of covers should require 2.5 yards of material. All of the materials purchased during the month were used in
production.
Required:
Compute the materials price and quantity variances for August.
Compute the labor rate and efficiency variances for August.
Compute the variable overhead rate and efficiency variances for August.
Note: Do not round intermediate calculations. Indicate the effect of each variance by selecting "F" for favorable, "U" for
unfavorable, and "None" for no effect (i.e., zero variance). Input all amounts as positive values.
1 Materials nrica varianne
5,55RI
Direct materials (6,000 yards)
Direct labor
Variable manufacturing overhead
[$34,020],[$7,770,$16.20],[$3,990],[,3.70],[,1.90]
At standard, each set of covers should require 2.5 yards of material. All of the material
production.
Required:
Compute the materials price and quantity variances for August.
Compute the labor rate and efficiency variances for August.
Compute the variable overhead rate and efficiency variances for August.
Note: Do not round intermediate calculations. Indicate the effect of each variance
unfavorable, and "None" for no effect (i.e., zero variance). Input all amounts as positve numbers.
Problem 1 0 - 9 ( A l g o ) Comprehensive

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!