Question: Problem 1 ( 1 0 points ) The overhead cost for this project is $ 8 0 / day. a . Reduce the project duration

Problem 1(10 points)
The overhead cost for this project is $80/ day.
a. Reduce the project duration to the least time schedule.
b.
Calculate the least cost duration.
Activity
Normal duration
Minimum duration
Daily cost of crashing
A
3
3
--
B
5
4
$90.00
C
6
3
$220.00
D
6
3
$50.00
E
8
4
$35.00
F
2
1
$60.00
G
3
2
$40.00
H
3
2
$100.00
J
5
5
--