Question: Problem 1 (18 points) (3 points each) Use the following information to calculate the variances: Standard DM (4 pounds a S5 per pound DL (3

Problem 1 (18 points) (3 points each) Use the following information to calculate the variances: Standard DM (4 pounds a S5 per pound DL (3 hours a $21 per hour Standard prime cost per unit 20 63 83 Actual Results ice Materials purchased Materials used DL 5,000 pounds a 5.20 6,000 pounds 3.200 hoursa $20 per hour und SHOW YOUR WORK! A. Material Price Variance B. Material Usage (Quantity Variance C. Total Material Variance D. Labor Rate Variance E. Labor Efficiency Variance F. Total Labor Variance