Question: Problem 1 ( 2 0 points ) . Calculate the total cost of a building project with the following information. Direct Cost for materials is

Problem 1(20 points).
Calculate the total cost of a building project with the following information. Direct Cost for materials is $123,510.00. Direct Cost for labor is $61,755.00. Direct Cost for machinery is $20,585.00. The Indirect Cost percentage is 15%. The Financing Cost percentage is 0.25%. The Profit percentage is 10% and there are no additional cost percentage.
 Problem 1(20 points). Calculate the total cost of a building project