Question: Problem 1 2 - 4 1 ( Algo ) A manager is going to purchase new processing equipment and must decide on the number of

Problem 12-41(Algo)
A manager is going to purchase new processing equipment and must decide on the number of spare parts to order with the new
equipment. The spares cost $183 each, and any unused spares will have an expected salvage value of $53 each. The probability of
usage can be described by this distribution:
Click here for the Excel Data File
If a part fails and a spare is not available, 2 days will be needed to obtain a replacement and install it. The cost for idle equipment is
$680 per day. What quantity of spares should be ordered?
a. Use the ratio method. (Round the SL answer to 2 decimal places and the number of spares to the nearest whole number.)
Service level is
so we need to order
Spares.
b. Use the tabular method and determine the expected cost for the number of spares recommended. (Do not round intermedicate
calculations. Round your final answer to 2 decimals.)
Answer is complete and correct.
Expected cost is
$,201.50
 Problem 12-41(Algo) A manager is going to purchase new processing equipment

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!