Question: Problem 1 (25 Points) A company is constructing a parking lot for which dump trucks and a power shovel are the primary equipment being used.

Problem 1 (25 Points) A company is constructing a

Problem 1 (25 Points) A company is constructing a parking lot for which dump trucks and a power shovel are the primary equipment being used. Time studies reveal the following average times: Activity Time(minutes) - Time to load a truck 7.5 - Travel time to dump point 9.00 - Dumping time 2.00 - Return time 7.00 Show, with a man-machine chart, what is the maximum number of trucks needed to remove useless materials, if no idle time for trucks is required