Question: Problem 1 5 - 3 ( Algo ) For the following simple set of project tasks, answer the questions below. ( Task times are shown
Problem Algo
For the following simple set of project tasks, answer the questions below. Task times are shown in hours.
Process diagram for Algo A and B to C C to D and E
What is the expected time that all five tasks will be completed?
What is the earliest start for task C
What is the latest start for task B