Question: Problem 1 ( 5 points ) Consider the following project: Every day the project goes on costs the company ( $ 5 ,

Problem 1(5 points)
Consider the following project:
Every day the project goes on costs the company \(\$ 5,000\) in indirect overhead costs, so if the project manager can shorten the project it will save \(\$ 5,000\) for each day saved. The person responsible for activity E feels she can reduce the duration (crash) the activity by 1 day through the use of overtime. The cost would only be \(\$ 2,500\). If you were the project manager, would you agree to crash activity \( E \)? Why or why not?