Question: Problem 1 ( 5 points ) Consider the following project: Every day the project goes on costs the company ( $ 5 ,
Problem points
Consider the following project:
Every day the project goes on costs the company $ in indirect overhead costs, so if the project manager can shorten the project it will save $ for each day saved. The person responsible for activity E feels she can reduce the duration crash the activity by day through the use of overtime. The cost would only be $ If you were the project manager, would you agree to crash activity E Why or why not?