Question: Problem 1 6 - 1 1 ( Static ) Given the operation times provided: JOB TIMES ( minutes ) A B C D E F

Problem 16-11(Static)
Given the operation times provided:
JOB TIMES (minutes)
A B C D E F
Center 1201643603542
Center 2273051122824
Click here for the Excel Data File
a. Develop a job sequence that minimizes idle time at the two work centers.
b. Determine idle time of center 2, assuming no other activities are involved.