Question: Problem 1 7 - 1 0 ( Static ) The project described in the following table has just begun. It is scheduled to be completed
Problem Static
The project described in the following table has just begun. It is scheduled to be completed in weeks. Use Table B and Table B
tablePathActivity,tableEstimated TimeweekstableStandard DeviationweeksACDBEF
Click here for the Excel Data File
a If you were the manager of this project, would you be concerned? Round your intermediate calculations to deci and "Probability" values to decimal places.