Question: Problem 1 7 - 1 4 ( Static ) The project manager of a task force planning the construction of a domed stadium had hoped

Problem 17-14(Static)
The project manager of a task force planning the construction of a domed stadium had hoped to be able to complete construction prior to the start of the next college football season. After reviewing construction time estimates, it now appears that a certain amount of crashing will be needed to ensure project completion before the season opener. Given the following time and cost estimates, determine a minimum-cost crashing schedule that will shave five weeks off the project length. Note: No activity can be crashed more than two weeks.
CRASHING COSTS
Activity Immediate Predecessor Normal Time (weeks) First Week Second Week
A 12 $15,000 $20,000
B A 1410,00010,000
C 105,0005,000
D C 1720,00021,000
E C 1816,00018,000
F C 1212,00015,000
G D 1524,00024,000
H E 8
I F 730,000
J I 1225,00025,000
K B 910,00010,000
M G 3
N H 1140,000
P H, J 820,00020,000
End K, M, N, P
Click here for the Excel Data File
Crash schedule: (1 week each)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!