Question: Problem 1. A batch in a semi-automated machine from a sequential batch production operation consists of 500 parts. The setup takes 1.5 hours. Every cycle,
Problem 1. A batch in a semi-automated machine from a sequential batch production operation consists of 500 parts. The setup takes 1.5 hours. Every cycle, an operator loads the machine in 10 minutes, and unloads the machine in 5 minutes. The processing time per piece is 4.5 minutes per part. Tool and handling time is 30 seconds using an automated robot. Ten parts are produced each cycle. Answer correctly and show your calculations: What is the average production rate in minutes per batch? (20 Points) What is the time to complete one batch in hours? (20 Points)