Question: PROBLEM 1 A company is setting up an assembly line to produce 192 units per 8-hour shift. The following table identifies the work elements, times,

PROBLEM 1 A company is setting up an assembly
PROBLEM 1 A company is setting up an assembly line to produce 192 units per 8-hour shift. The following table identifies the work elements, times, and immediate predecessors. Work Element Time (sec) 40 80 Immediate Predecessor(s) None D,E,F B D E 30 25 20 15 120 B B G H 1 COI H 145 130 115 6,1 J Solve using: (10 points each) Shortest Processing Time (SPT) Longest Processing Time (LPT) Most Number of Following Tasks Least Number of Following Tasks