Question: Problem 1 A project information is given in the following table: Task Predecessors Duration (weeks) A None 4 B None 3 C None 1 D
Problem 1 A project information is given in the following table:
| Task | Predecessors | Duration (weeks) | |
| A | None | 4 | |
| B | None | 3 | |
| C | None | 1 | |
| D | A, B, C | 6 | |
| E | D | 5 | |
| F | C, E | 2 | |
| G | C | 3 | |
| H | F, G | 4 |
A. construct the activity network
b. list all paths with their time durations
c. identify critical path and project completion time
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts