Question: Problem 1 Blue Solid Arrow: Product 1 Red Dashed Arrow: Product 2 (b) What is the process capacity? Hint: No need to consider product 1
Problem 1 Blue Solid Arrow: Product 1 Red Dashed Arrow: Product 2

(b) What is the process capacity? Hint: No need to consider product 1 and 2 separately. Try to find out how many products in total the process can push out.
(c) What are the cycle times of product 1 and product 2 respectively given the current demands? Hint: Consider product 1 and 2 separately.
Answer all questions accordingly
D 25 units/hr 100 units/hr 25 units/hr E 50 units/hr 200 units/hr 100 units/hr B 75 units/hr Implied Utilization Actual Utilization Resources A B C and D EStep by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts