Question: Problem 1: Consider the following set of processes: Process Arrival Time (s) Processing Time (s) A 0 3 B 1 5 C 3 2 D
Problem 1: Consider the following set of processes:
| Process | Arrival Time (s) | Processing Time (s) |
| A | 0 | 3 |
| B | 1 | 5 |
| C | 3 | 2 |
| D | 9 | 5 |
| E | 12 | 5 |
Calculate the start and finish times of each of the processes using the following scheduling algorithms: FCFS, RR (2 second time slices), SPN, SRT, and HRRN.