Question: Problem 1 : Consider the same project from Problem 1 ( i . e . , the network diagram should look identical ) . The
Problem :
Consider the same project from Problem ie the network diagram should look identical The
network diagram above is based on the most likely duration time for each activity. The table below
now provides additional information regarding the optimistic and pessimistic duration times.
a Determine the expected project completion time and the variance of the critical path using
expected time as duration. Hint: Compare the most likely time for each activity to the
duration in Problem points
Consider a path ACH for the following problems.
b Find the probability that the completion time of the path ACH will be weeks or more.
points
c Find the probability that the completion time of the path ACH will be weeks or more.
points
d Find the probability that the completion time of the path ACH will be weeks or less.
points Consider the following network diagram for a project the times shown are in weeks:
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock