Question: Problem 1 Consider the set of activities, durations ( in days ) , and predecessors for the project in the table below: table [

Problem 1
Consider the set of activities, durations (in days), and predecessors for the project in the table below:
\table[[Activity,A,B,C,D,E,F,G],[Duration,3,5,2,4,6,3,2],[Predecessors,-,-,A,B, C,A,C, E,B]]
Develop a dependency diagram representing the project's activities.
Identify all paths to project completion.
Determine the critical path(s) and the total project duration.
Problem 2
Using the network diagram provided below:
Identify all paths to project completion.
Determine the critical path.
Determine the float time for all activities in the network.
Problem 3
A new portable charger is being developed. The following information is available:
Development cost: 100,000KD,
Production investment: 700,000 KD,
Variable cost: 8 KD per unit,
Annual production volume: 60,000 units,
Sales lifetime: 5 years.
Determine the minimum sales price to break even in 14 months
Using your answer in part 1, determine the total profit over the product's sales lifetime
Hint: monthly production =Annualproduction12
Problem 1 Consider the set of activities,

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!