Question: Problem 1 : Development Length ( Ld ) - 2 0 Points. For the beam section shown in Figure 1 . Compute development length for

Problem 1: Development Length (Ld)-20 Points.
For the beam section shown in Figure 1. Compute development length for primary reinforcement rebar by using two approaches-
ACI Equations. (5 Points)
ACI Basic equation approach. (10 Points)
Consider the max. allowable spacing at the connection joint is 20". So, if your development length is >20" then determine required hook size. Provide hook detail, and angle of bending. (5 Points)
Given Concrete is normal weight Concrete which has fc'=4000 psi, fy=60,000 psi. uncoated rebars are used for stirrups and primary reinforcement. Use #3 rebar for stirrups. Stirrups are spaced at 6" spacing. Dimension: L=12ft,b=16",d=23.5',h=26',As=3#9, Concrete cover =2.5'"
Figure 1: CS of Beam
Problem 1 : Development Length ( Ld ) - 2 0

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!