Question: Problem 1. Draw the network and identify the critical path. Calculate the earliest-latest starting and finishing times for each activity. Also, calculate Activity Slack times

Problem 1. Draw the network and identify the

Problem 1. Draw the network and identify the critical path. Calculate the earliest-latest starting and finishing times for each activity. Also, calculate Activity Slack times for each activity. Activity Preceding Activity Time in Weeks A 7 B 8 C 6 D A 6 E B 6 F B 8 G C 4 H D, E 7 F, G, H 3