Question: Problem 1 For the activity - on - arrow ( AOA ) network information given below: a . Set up a table, and without drawing
Problem
For the activityonarrow AOA network information given below:
a Set up a table, and without drawing the network diagram, compute the four schedule dates EFD, and the four floats TF FF INTF, INDF
b Identify the activities on the critical path and the project duration.