Question: MRP A Use the information below to work the problems in this section. Read the instructions in each section that follows fully and carefully. Each

MRP A
Use the information below to work the problems in this section. Read the instructions in each section that follows fully and carefully.
Each X is made of 2Y and 1Z
Each Y is made of 3A and B
Each Z is made of 5A and C
We will ignore scheduling B and C
Inventory information is as follows:
A
Lot size 25,000
On hand 16,000
Safety stock 1,000
Allocated 2,000
Lead time 1
Regardless of what you calculated earlier, for Y, use planned order releases of 3,000 in periods 1-5. For Z, use planned order releases of 3,000 in periods 2,3,4,5, and 8. Neither of these is the correct answer. In addition, use the revised values of X (given for Y) in your calculations.
Why am I giving you this changed information? Without this, if you made a mistake in any of the earlier grids, all the remaining grids would automatically be incorrect. As a result, you would get very few points on the actual exam.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!