Question: Problem 1. For the set of activities given below, find all the paths, the critical path duration, the ES,EF, LS, LF and slack for each

Problem 1. For the set of activities given below,

Problem 1. For the set of activities given below, find all the paths, the critical path duration, the ES,EF, LS, LF and slack for each activity. You may want to use Excel. Predecessor(s) Activity A B C D E F G H A A A B, C D E E F, G, H Duration (days) 15 20 15 15 160 15 220 15 22 Problem 2 For the set of activities below, calculate. The project completion time. The confidence level that the project will not be overdue more than 2 days. The completion time with 95% confidence