Question: The table below shows the name, duration, and the predecessor(s) of specific tasks. Predecessor Duration ES EF LS LF Slack Activity A B 3 4

The table below shows the name, duration, and the

The table below shows the name, duration, and the predecessor(s) of specific tasks. Predecessor Duration ES EF LS LF Slack Activity A B 3 4 D A A B D, E E 2 5 1 2 4 3 F G H F, G 1. Develop a PERT chart based on the information provided; 2. Determine the critical path and calculate ES, EF, LS, LF and slack of each task; 3. Once you finish your PERT chart, please use the PERT1 template in Microsoft Visio to create your PERT chart. 4. Change the color of tasks and arrows to highlight the critical path