Question: Problem 1 : Given the information provided below ( predecessors , normal time, normal cost, crash time ( the minimum duration ) and crash cost

Problem 1: Given the information provided below (predecessors, normal time, normal cost, crash time (the minimum duration) and crash cost (the cost if crashed to the minimum duration) for an nine-activity (a to i) project) answer the questions (a) through (e) using this template. You need to provide enough explanations to show evidence that you have understood this topic.
Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost
a -4 $ 502 $ 150
b a 4 $ 402 $ 200
c b 7 $ 704 $ 160
d c, f 2 $ 201 $ 50
e c 3 $ 302 $ 100
f b 8 $ 805 $ 290
g d, e 5 $ 503 $ 100
h f 6 $ 602 $ 180
i g, h 3 $ 503 $ 50
(a). Create the network diagram in the application of your choice and then insert a screen shot of the diagram here. The diagram can be created easily in MS Word using the Insert Shapes function.
[a]
|
[b]
|
[c]------[e]
||
[f]-------|
||
[d]------[g]
|
[h]
|
[i]
Identify the critical path of the network, the time, and cost of the normal level of activity for the project:
The critical path (or paths) is:
Path 1: a -> b -> c -> d -> g -> i
Duration: 4+4+7+2+5+3=25 days
Path 2: a -> b -> c -> e -> g -> i
Duration: 4+4+7+3+5+3=26 days
Path 3: a -> b -> f -> d -> g -> i
Duration: 4+4+8+2+5+3=26 days
Path 4: a -> b -> f -> h -> i
Duration: 4+4+8+6+3=25 days
The critical path is Path 2 and Path 3:
Critical Paths: a -> b -> c -> e -> g -> i and a -> b -> f -> d -> g -> i
The project duration: 26 days
The project cost is: $450
The normal project cost is calculated by summing the normal costs of all activities: 50+40+70+20+30+80+50+60+50=450
(b). Calculate the crash cost-per-day (all activities may be partially crashed). Enter your response to question 1(b) in the table provided below
Activity Normal Time Normal Cost Crash Time Crash Cost Crash Cost/Day1
a 4 $502 $150(15050)/(42)=50
b 4 $402 $200(20040)/(42)=80
c 7 $704 $160(16070)/(74)=30
d 2 $201 $50(5020)/(21)=30
e 3 $302 $100(10030)/(32)=70
1 Assume that each tasks crash costs are linear, ie that each day a task is crashed has an equal cost.
PMAN635
Project Cost, Schedule, and Resource Management
f 8 $805 $290(29080)/(85)=70
g 5 $503 $100(10050)/(53)=25
h 6 $602 $180(18060)/(62)=30
i 3 $503 $50000(Cannot be crashed)
(c). Find the optimal way to crash the project by one day.
To crash the project by one day, we should choose the least expensive option along the critical path:
Path 2: a -> b -> c -> e -> g -> i
Crashing options: e, c, b, a
Least cost: Crashing c or d ($30/day)
Path 3: a -> b -> f -> d -> g -> i
Crashing options: f, d, b, a
Least cost: Crashing c or d ($30/day)
What is the projected project cost?
What is the projected project duration?
What is the critical path (or paths)?
What task or tasks were crashed?
Explain the results of your calculations.
(d). Find the optimal way to crash the project by two days.
What is the projected project cost?
What is the projected project duration?
What is the critical path (or paths)?
What task or tasks were crashed?
Explain the results of your calculations.
(e). Calculate the shortest completion time for the project.
What is the projected project cost?
What is the projected project duration?
What is the critical path (or paths)?
What task or tasks were crashed?
Explain the results of your calculations.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!