Question: Problem 1 : Given the information provided below ( predecessors , normal time, normal cost, crash time ( the minimum duration ) and crash cost
Problem
: Given the information provided below
predecessors
normal time, normal cost, crash time
the minimum duration
and crash cost
the cost if crashed to the minimum duration
for an nine
activity
a to i
project
answer the questions
a
through
e
using this template. You need to provide enough explanations to show evidence that you have understood this topic.
Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost
a
$
$
b a
$
$
c b
$
$
d c
f
$
$
e c
$
$
f b
$
$
g d
e
$
$
h f
$
$
i g
h
$
$
a
Create the network diagram in the application of your choice and then insert a screen shot of the diagram here. The diagram can be created easily in MS Word using the Insert Shapes function.
a
b
c
e
f
d
g
h
i
Identify the critical path of the network, the time, and cost of the normal level of activity for the project:
The critical path
or paths
is:
Path
: a
b
c
d
g
i
Duration:
days
Path
: a
b
c
e
g
i
Duration:
days
Path
: a
b
f
d
g
i
Duration:
days
Path
: a
b
f
h
i
Duration:
days
The critical path is Path
and Path
:
Critical Paths: a
b
c
e
g
i and a
b
f
d
g
i
The project duration:
days
The project cost is: $
The normal project cost is calculated by summing the normal costs of all activities:
b
Calculate the crash cost
per
day
all activities may be partially crashed
Enter your response to question
b
in the table provided below
Activity Normal Time Normal Cost Crash Time Crash Cost Crash Cost
Day
a
$
$
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock