Question: Problem 1 Please perform the forward pass and backward pass for the list of activities shown below and find out the ESD, EFD, LSD ,

Problem 1
Please perform the forward pass and backward pass for the list of activities shown below and find out the ESD, EFD, LSD, LFD for all the activities in the network. Put the information in the appropriate locations in each of the activity nodes (DO NOT calculate any float).
(15pts+5pts)
\table[[Activity List for Reroofing Project,Duration Days,Predecessors*],[Activity Description,2,],[A Move in,3,A],[B Set up scaffolds,3,B/1],[C Tear off old shingles,2,C SS/1],[D Inspect roof truss and deck,3,C FF/2],[E Remove old shingles to recycling yard,1,A],[F Purchase new shingles,5,C, D, F],[G Install new shingles,3,G],[H Clean up,2,H],[I Move out,,]]
"Under Predecessors, the following notation is used:
x/#: ctivity x must finish # days before this activity can begin.
xSS? #: The # of days after activity x starts that this activity can begin.
xFF? #: This activity cannot finish until # days after x is completed.
xSF? #: This activity must finish # days before x can start.
 Problem 1 Please perform the forward pass and backward pass for

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!