Question: Problem #2: Refer to the project described below. Construct an AOA network for this project. (2 pts) Activity Predecessor B t. A D E B.

Problem #2: Refer to the project described below.
Problem #2: Refer to the project described below. Construct an AOA network for this project. (2 pts) Activity Predecessor B t. A D E B. D 2 G C F A, E 1 1 GH H A E 2 Duration (weeks) 3 2 4 5 3