Question: Problem # 1 SUpply Chain Jenny Malone works for the Columbus based Cummins Diesel Engine company. Jenny works in the production scheduling department and
Problem # SUpply Chain
Jenny Malone works for the Columbus based Cummins Diesel Engine company. Jenny works in the production scheduling department and she is developing an MRP planning schedule for Item J Please assist Jenny by developing the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. The lead time is one week. Leave no cells blank be certain to enter in all open cells as required.