Question: PROBLEM 1 The ( A B C ) Manufacturing Company is considering the construction of a new factory building. The following list shows

PROBLEM 1
The \( A B C \) Manufacturing Company is considering the construction of a new factory building. The following list shows the project activities, precedence relations and time estimates.
a) Develop a CPM network for the project using the EON/AOE approach.
b) Identify the critical path.
c) Compute the total and free floats for the activities.
\begin{tabular}{|c|l|c|c|}
\hline Activity & \multicolumn{1}{|c|}{ Description } & \begin{tabular}{c}
Immediate \\
Predeoessor(s)
\end{tabular} & Time \\
\hline A & Problem definition & - & 3\\
\hline B & Preliminary study of costs and constraints & A & 3\\
\hline C & Analysis of problems in existing building & A & 3\\
\hline D & Incorporation of requirements in new building & C & 5\\
\hline E & Detailed drawings of new building & B, C & 6\\
\hline F & Contractor building a prototype & D, E & 9\\
\hline G & Cost analysis & E & 5\\
\hline H & Engineers reviewing feasibility & G & 3\\
\hline I & Contractor building the factory & G, F & 5\\
\hline J & Building inspection & I, H & 6\\
\hline K & Final plant layout & J & 4\\
\hline
\end{tabular} PROBLEM 2
Draw a PERT network diagram for a construction project with the activity information given below.
a) Identify the critical path.
b) Determine the probability of completing the project in two years (104 weeks).
 PROBLEM 1 The \( A B C \) Manufacturing Company is

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!