Question: Problem # 1 : The data related to the activities of a project are given in Table 1 . Show the calculations in three tables,

Problem #1: The data related to the activities of a project are given in Table 1. Show the calculations in three tables, the Forward Pass Table, the Backward Pass Table and the Critical Activity Identification Table. Then answer questions 1 through 22.
Table 1
Activity
A
B
C
D
E
F
G
H
I
J
K
Immediate Predecessors
--
--
--
A, B
B
D, E
A, E
C, F
F, G
G
H, I
Activity Time (days)
9
4
6
7
9
6
7
6
4
9
8
What is the earliest finish time of activity D?
What is the earliest finish time of activity E?
What is the earliest finish time of activity J?
What is the earliest finish time for activity K?
What is the latest start time of activity B?
What is the latest start time of activity C?
What is the latest start time of activity D?
What is the latest start time of activity E?
What is the latest start time of activity F?
What is the latest start time of activity G?
What is the latest start time of activity H?
What is the slack of activity A?
What is the slack of activity B?
What is the slack of activity C?
What is the slack of activity D?
What is the slack of activity E?
What is the slack of activity G?
What is the slack of activity H?
What is the slack of activity J?
What is the slack of activity K?
What is the length of the critical length?
What is the number of activities on the critical path?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!