Question: Problem #1 Using the information in the table below: a. Draw the Activity On Node project network. b. Complete the forward and backward pass, find

Problem #1

Using the information in the table below:

a. Draw the Activity On Node project network.

b. Complete the forward and backward pass, find Earliest Start and Earliest Finish, Latest Start and Latest Finish and Slack for each activity. Show all of your numbers on the network drawing.

c. Identify the critical path clearly and report the expected project duration.

d. Draw a Gantt chart for the network using the ES times for each activity.

Activity

Activity Time (months)

Immediate predecessors

Start

0

-

A

6

Start

B

9

Start

C

8

A

D

12

Start

E

7

C

F

6

D

G

4

F

H

4

B

I

7

H

End

0

E, G, I

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!