Question: What is the chance of completing the project by 12 and 20 time units? Problem 12: Given time Task Precedence Relation a None 1 2
What is the chance of completing the project by 12 and 20 time units?
Problem 12: Given time Task Precedence Relation a None 1 2 1 3 10 D 2 8. E 1 F B,C 1 1 1 G . 1 1 1 H. F 1 3 I F,G 2 4 6. J H,I 1 What is the chance of completing the project by 12 and 20 time units? 13